Theater Orpheus – Apeldoorn

Replacement of controls for the theatrical fly system

Client

Theatre & Convention Center Orpheus

Hall

Large hall, Middle hall

Architect

Floor Area

Project Description

The controls of the theatrical fly system no longer fully complied with applicable regulations. In addition, the controls had exceeded their maximum service life, which also resulted in malfunctions. The decision was made to replace the controls (including brakes) of the fly system of the Large Hall (Hanos Hall) and Middle Hall (Rabobank Hall) of Theater Orpheus, with the aim of ensuring that the renewed installation meets both the current user requirements and operational reliability as well as “the current state of the art”.


Our advice
For the Research, Consulting and Procurement Guidance component:

  • QuickScan examination of existing plant
  • Preparation of the statement of work (specifications).
  • Establishing grounds for exclusion and award criteria
  • Supervise site inspections
  • Note of Information Reply
  • Reviewing tenders

 

For Implementation Guidance:

  • Kick-off meeting and project plan review
  • Construction supervision and interim recordings
  • Quotation request inspection (TüV or Lift Institute)
  • Supervising commissioning inspection and delivery.